Chap 7 Realistic Scheduling
IDENTIFY TASK RELATIONSHIP
- Arrange the order of work packages and set milestone as useful marker –
- For my project, I need to breakdown the individual functions among design, backend support and system integration and then further verify what’s the associated relationship
ESTIMATE WORK PACKAGE
- Total amount of labor and equipment need to allocate for the project. Also include finding the balance of among cost, schedule and quality of the project.
MILESTONE
To highlight the breakthrough of major tasks being accomplished.
My project embedded 4 major milestones
- Design Control of Power Supply to TC Chamber Interface
- Program Chamber Profile
- Design Fault Triggering / Circuit Protection
- Finished day of hardware build
COST ESTIMATION
- Budget of Labor, Equipment and Materials
CRITICAL PATH
- Define as the task cannot have extra hours being spent otherwise the original schedule will be revised. This means any of tasks in this path with zero or negative float.
RESOURCE LEVELING
- Identify resource peaks and redistribute the resource make job more productive without affecting the due date.
The outline of my project schedule as follows TASK NAME | Labor hrs |
| Design Power Temper Cycle (TC) Test | |
| 1.0 Spec requirement Review | 6 hrs |
| 2.0 Power estimation and HW dimension check | 4 hrs |
| 2.1 System features and utility arrangement check | 4 hrs |
| 2.1.1 Evaluate Existing Chamber Features | 4 hrs |
| 2.1.1.1 Design Control of Power Supply to TC Chamber Interface | 20 hrs |
| 2.1.1.2 Chamber air flow check | 16 hrs |
| 2.1.1.3 Program Chamber Profile | 8 hrs |
| 2.1.2 Evaluate Power supply meet power requirement | |
| | |
| 3.0 System integration trial run | 120 hrs |
| 4.0 Power TC Burn-in schematic (product specific) | 8 hrs |
| 4.1 Design Fault Triggering / Circuit Protection | 8 hrs |
| 4.2 Estimate total power consumption (product specific) | 4 hrs |
| 4.3 Verification of 1st trial run samples | 12 hrs |
| 5.0 Burn in Board Hardware | 2 hrs |
| 5.1 Layout motherboad | 8 hrs |
| 5.2 Layout daughter card | 8 hrs |
| 5.3 Outsource to contractor for hardware build | 1 mth |
This project schedule outline is terrific - able to justify the labor cost effectively.